Test points stay steady even as exam details shift, and Prep4SureReview has already compiled and sorted them for you. Every 2026 purchase includes 365 days of free updates to the SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 practice questions.
SAP C-TSCM42-67 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Enterprise Structure and Master Data in Production Planning | - Work centers and routings - Material master and BOM (Bill of Materials) - Organizational units in SAP PP |
| Production Orders and Execution | - Order confirmations and goods movements - Order creation and release - Order settlement and status management |
| Material Requirements Planning (MRP) | - Exception messages and evaluation - Lot sizing and procurement proposals - MRP types and planning run |
| Kanban and Just-in-Time (JIT) Production | - Kanban control cycles - JIT replenishment concepts |
| Capacity Planning and Shop Floor Control | - Capacity evaluation and leveling - Detailed scheduling |
| Demand Management and Sales & Operations Planning | - Sales and operations planning integration - Planned independent requirements (PIR) |
SAP C-TSCM42-67 Exam FAQ: Considerate Answers
SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 is an official SAP exam, registered under the code C-TSCM42-67. Passing it earns the SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 certification at the Associate level. It also connects to SAP Certified Application Associate - Production Planning & Manufacturing, SAP Certified Application Associate - SAP ERP. In a fast-developed industry, this certificate is a promise to your career and your next promotion.
Basic knowledge of SAP ERP navigation and production planning processes is recommended; prior SAP ERP or SAP PP experience is beneficial but not mandatory.
Vendor policies do evolve, so confirm the current conditions before you register.
The SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 exam contains 80 questions within 180 minutes. Former customers share a consistent secret: two or three regular hours of daily practice beat sporadic cramming. The Prep4SureReview engine covers every important test point, so a steady routine builds both knowledge and the pacing the clock demands.
Passing SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 requires 65%, and the official fee is USD 550 (varies by region). Retakes bill the full USD 550 (varies by region) again, so treat readiness as something to verify, not assume: when your Prep4SureReview practice scores clear the requirement day after day, you are ready to book.
Registration for SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 runs through the official channels below.
One scheduling detail: the exam is delivered Online proctored exam via SAP Certification Hub.
Yes, SAP recommends the following training for SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 candidates.
- SAP Learning Hub - Production Planning (PP)
- SAP ERP 6.0 EHP7 Production Planning and Manufacturing Training
Whichever training you follow, practice daily with the 108 questions in the Prep4SureReview C-TSCM42-67 package; regular hours with real exam-style items are what turn preparation into a pass.
SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 is divided into 6 official domains, led by Production Orders and Execution, Kanban and Just-in-Time (JIT) Production, and Enterprise Structure and Master Data in Production Planning. The full outline is above; while details shift over time, the main test points stay steady, and we have already sorted them for you.
Yes and yes. If you are a little suspicious, download the free demo of the SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 questions and check the material before deciding. After purchase, updates are free for 365 days, with new versions sent to you as soon as test points change; after expiry, extending the update service costs 50% of the regular price.
We promise it in writing: a 100% money-back guarantee under defined conditions. Take the SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 exam within 60 days of purchase; if you fail, claim a full refund according to your transcript by submitting a scanned enrollment slip and the official Score Report PDF within 2 days of the exam, processed within 7 days. The exam must match your product, candidate and payer names must match, and attempts within 3 days of purchase, unused downloads, free materials, and expired orders are excluded. Alternatively, switch freely to other exam material: two equivalent products, free, with updates retained on your original purchase.
Delivery is instant: files unlock for download at payment and are emailed within one minute, so there is no wasted time between ordering and studying. If nothing arrives within 2 hours, check spam and contact our 24/7 aftersales agents. Installation is unlimited.
SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 Sample Questions:
Which property applies for consumption with planning strategy 40 (planning with final assembly)?
- A. Consumption can reduce the total originally planned production quantity.
- B. Consumption takes place with the planning material.
- C. Consumption can increase the total originally planned production quantity.
- D. Consumption creates a static and binding assignment between the planned independent requirements and the customer requirements for the entire procurement process.
Correct Answer: C 🗳️
Which of the following activities within the KANBAN procedure normally triggers subsequent stock posting of the goods receipt?
- A. Set "Container full"
- B. Set "Container in process"
- C. Set "Container empty"
- D. Set "Container in transport"
Correct Answer: A 🗳️
What is a feature of the simu-lation mode for material requirements planning in SAP ECC?
- A. It triggers multilevel bottom-up scheduling.
- B. It calculates the delay time which may occur in planning.
- C. It posts planning results to the database automatically.
- D. It propagates exception messages from a component to the finished product.
Correct Answer: B 🗳️
In which of the following objects can you activate backflushing of components if you want to use this functionality during order confirmation? (Choose three.)
- A. Material Master (Component)
- B. Production Scheduling Profile
- C. Routing
- D. Work Center
- E. Material Master (Finished Product)
Correct Answer: A,C,D 🗳️
The final assembly of a finished product should only be triggered when a customer order arrives.
Which planning strategy for the finished product do you use?
- A. Planning at the assembly level (strategy 70)
- B. Planning with make-to-stock (strategy 10)
- C. Planning with final assembly (strategy 40)
- D. Planning without final assembly (strategy 50)
Correct Answer: D 🗳️
Viewing page 1 out of 22 pages.
Viewing questions 1-5 out of 108 questions.