CompTIA PK0-400 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Project Management Concepts | 33% | - Scheduling and planning
|
| Topic 2: Project Lifecycle Phases | 30% | - Monitoring and controlling
|
| Topic 3: Communication and Change Management | 19% | - Communication methods
|
| Topic 4: Project Tools and Documentation | 18% | - Quality and analysis tools
|
Frequently Asked Questions About CompTIA Project+
The CompTIA Project+ questions are written and organized by senior experts and experienced specialists so that your study time concentrates on the most test-relevant knowledge. Instead of spreading your effort across endless coverage, you practice what the PK0-400 exam actually weighs, which raises your learning efficiency session by session.
The real PK0-400 exam gives you 90 minutes minutes for Maximum 90 questions questions. Rehearsing under the same conditions on the Prep4SureReview engine builds the pacing you will rely on.
- Communication and Change Management (19%)
- Project Tools and Documentation (18%)
- Project Management Concepts (33%)
Let the weights decide where your hours go first.
Three versions cover different working lives. The PDF downloads for learning at any time. The PC test engine runs on unlimited computers, so you can study on screens at home and at the workplace. The online engine works on any electronic equipment, with no device limit and offline use supported, so practice never depends on your location.
The package contains 96 practice questions for the PK0-400 exam, all verified by senior experts and organized for focused, efficient revision.
To pass PK0-400 you need 710 (on a scale of 100-900), and the official exam fee is $348–$399 USD. Fixing both figures early keeps your target concrete and your budget planned.
CompTIA Project+ Official Registration: register for PK0-400
Pearson VUE Exam Scheduling: register for PK0-400
CompTIA CertMaster Learn (Project+): Visit official page
CompTIA Official Study Guide: Visit official page
No formal prerequisites required; recommended 6–12 months project management experience or equivalent knowledge
CompTIA Project+ Sample Questions:
The project manager for a TV tower construction project receives notification that a strong storm is expected the following week.
Which of the following should the project manager do NEXT?
- A. Evaluate the risk, inform major stakeholders about the problem, and issue a change request immediately.
- B. Evaluate the risk, reschedule all outdoor tasks for a later time, and inform major stakeholders.
- C. Evaluate the risk, fill in the issue log, and communicate it according to the communication plan.
- D. Evaluate the risk, develop a mitigation plan, and communicate it according to the communication plan.
Correct Answer: D 🗳️
The project manager has noticed a vendor is not performing in accordance with the SLA.
Which of the following items should the project manager use to highlight the vendor's areas of poor performance?
- A. WBS
- B. PERT
- C. Post-project evaluation
- D. Balanced score card
Correct Answer: D 🗳️
The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date.
To alter the pace of the project, which of the following should the project manager do FIRST?
- A. Give approval for the change requested by the project sponsor.
- B. Ask the project sponsor to change the request.
- C. Document the change request from the project sponsor.
- D. Deny the request from the project sponsor.
Correct Answer: C 🗳️
Which of the following is a key aspect of the Agile project management methodology?
- A. Daily standup meetings
- B. Test-driven
- C. Defined list of requirements
- D. Short project durations
Correct Answer: A 🗳️
An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs.
Which of the following actions should the project manager take?
- A. Accept the new power output.
- B. Submit a new change request.
- C. Initiate the regression plan.
- D. Add remediation to the schedule.
Correct Answer: C 🗳️